|
|||||||||||||||||||||||
|
Waterfront Update Archive
Fall 2007
Atlantic Richfield Company has completed the first part of the multimillion dollar investigation that is dominating its 2007 activities on the One River Street site. The second part of that work will continue later in 2007. The investigation, undertaken at the request of NYSDEC, is intended to provide additional information as the agency selects a final remedy for the clean-up of the Hudson River.
Fall 2006
ARC submits 50% remedial design plan to NYSDEC
ARC has submitted a 50% remedial design plan to NYSDEC in August 2006. That plan will identify and discuss many of the critical design issues required to complete the environmental remedies to be conducted at the site.
For more information, click here.
While the report found that no buildings merited historic landmark preservation status, it did cite Buildings 51 and 52 as good examples of Hudson River industrial architecture and noted that the water tower had significance for the community. The plan revealed the significant challenges to preserving these structures during the environmental remediation of the site. For more information, click here. Summer 2006
Hutton & Associates, the well-respected architectural firm was hired by the Atlantic Richfield Company to conduct a study of three structures on the waterfront -- the water tower and Buildings 51 and 52. This study will analyze the condition of the buildings, their historic features and the feasibility of preservation. The report is expected to be finalized and presented to the community in June 2006.
The environmental engineering firms Haley & Aldrich and ENSR are working on the Remedial Design stage of the work at the One River Street site. The boring and test pit phase of the Pre-Design Investigation (PDI) has now been completed and work continues on the design itself. The drilling has provided soil data for use by geotechnical engineers during design of the structural element, such as sheet pile bulkheads along the waterfront and excavation support systems. Air monitoring was performed meticulously throughout the drilling phase to ensure that any contaminants did not impact the health and safety of the workers or community residents. The other part of the investigation is focused on improving the definition of the proposed excavation areas, primarily in the northwest corner of the site.
Video surveillance cameras continue to be used throughout the One River Street site for security purposes. These high-tech cameras are fully operational and are monitored by our security personnel 24 hours a day, 7 days a week, for the mutual safety of community residents and the workers January 2006
Happy New Year from the Atlantic Richfield Company and all of us at the One River Street site.
Hutton & Associates, the well-respected architectural firm hired by the Atlantic Richfield Company to conduct a study of three structures on the waterfront -- the water tower and Buildings 51 and 52, are expected to present their findings this month. This study will analyze the condition of the buildings, their historic features and the feasibility of preservation. The report is expected to be finalized and presented to the community before the end of January 2006. The environmental engineering firms Haley & Aldrich and ENSR are working on the Remedial Design stage of the work at the One River Street site. The boring and test pit phase of the Pre-Design Investigation (PDI) has now been completed and work continues on the design itself. The drilling has provided soil data for use by geotechnical engineers during design of the structural element, such as sheet pile bulkheads along the waterfront and excavation support systems. Air monitoring was performed meticulously throughout the drilling phase to ensure that any contaminants did not impact the health and safety of the workers or community residents. The other part of the investigation is focused on improving the definition of the proposed excavation areas, primarily in the northwest corner of the site. Video surveillance cameras continue to be used throughout the One River Street site for security purposes. These high-tech cameras are fully operational and are monitored by our security personnel 24 hours a day, 7 days a week, for the mutual safety of community residents and the workers on site. Happy New Year from the Atlantic Richfield Company and all of us at the One River Street site. Fall/Winter 2005
ARC has hired Hutton & Associates, a well-respected architectural firm with a strong background in the field of historic preservation to conduct a study of three structures on the waterfront -- the water tower and Buildings 51 and 52. This study will analyze the condition of the buildings, their historic features and the feasibility of preservation. The report is expected to be finalized and presented to the community between mid-December 2005 and early January 2006.
The Atlantic Richfield Company has selected the environmental engineering firms Haley & Aldrich and ENSR for the Remedial Design stage of the work at the One River Street site. These companies are working on the boring and test pit phase of the Pre-Design Investigation (PDI), as of mid-September 2005. This phase of the remedial design, which is expected to take eight weeks, has two distinct components that require the use of drilling equipment and backhoes. Most of the investigation is focused on developing soil data for use by geotechnical engineers during design of the structural element, such as sheet pile bulkheads along the waterfront and excavation support systems. The other part of the investigation is focused on improving the definition of the proposed excavation areas, primarily in the northwest corner of the site. Air monitoring will also be performed meticulously throughout the investigation to ensure that any contaminants do not impact the health and safety of the workers or community residents.
Video surveillance cameras are located throughout the Monday, August 8th 2005 - Friday, August 12th 2005
Monday, August 1st 2005 - Friday, August 5th 2005
Monday, July 18th 2005 - Friday, July 29th 2005
Monday, July 11th 2005 - Friday, July 15th 2005
Monday June 27th 2005 - Friday July 1st 2005
Asbestos abatement on buildings number 15, 18, 19, 22A and 79A is now completed. Beginning the week of Monday, June 27th, 2005 demolition of building 15 is to commence and is expected to be completed in the next few weeks as part of clearing the way for remediation of the One River Street site.
|
|
||||||||||||||||||||||